Meadowbrook Subdivision

Project Summary

This subdivision will feature 210 buildable single-family lots once complete.

Developer:

Stu Stenger

This subdivision will contain 210 buildable single-family lots once complete. There is no anticipated completion date for this project.

May 8, 2024

Pre-Construction Meeting Held

Phase 4 plans have been approved. Meadowbrook Phase IV will start infrastructure improvements in 4-6 weeks.  This is the final phase of Meadowbrook.

February 26, 2024

Phase 4

Phase 4 is under review. This phase will consist of 78 single-family residential lots.

Photo shows a field where Meadowbrook Phase 4 will be built

February 26, 2024

Phase 3

Meadowbrook Phase 3 has a final plat recorded with the City of Nixa. Construction of houses anticipated to begin soon.

Photo shows empty lots waiting for the construction of homes. Roadway infrastructure is fully built-out.

June 7, 2023

Construction Underway

With phases 1 and 2 complete, construction on homes has begun.

Phase 1

Phase 1

Phase 2

Phase 3

Photo shows empty lots waiting for the construction of homes. Roadway infrastructure is fully built-out.

Phase 3

Phase 3

Photo shows a field where Meadowbrook Phase 4 will be built

Phase 4