Northview Road Extension

Project Summary

This project involves expanding Northview and installing a larger roundabout at Northview Road & Gregg Road.

Project Quick Facts

Budget:

Roundabout: $243,000

Road Extension & Intersection: $592,804

Contractor(s):

Blevins Asphalt

Completion Date:

The roundabout was completed by August 2023.

The entire project, including the road expansion, was completed by December 2023.

Project Documents

This is a combination of two projects:

  • The expansion of the roundabout at Northview Rd. and Gregg Rd.
  • The widening of Northview Rd. from Tractor Supply in Nixa to just west of Old Wilderness Rd., which will include a new intersection and turn lanes to Old Wilderness.

December 14, 2023

Project Compete!

The roundabout at Gregg Rd. and Northview, and the Northview extension just west of Hwy 160 are open to traffic. This project is complete, but please be aware of construction clean up and minor striping work.

November 8, 2023

Northview Rd. Closed at Old Wilderness Beginning Nov. 13th

Drivers in Nixa should prepare to use alternate routes beginning November 13 if using Northview Rd. to the west of Tractor Supply. This closure is for the Northview Road Improvement Project which will widen the road to 3 lanes between Old Wilderness Rd and Kenneth St. This section of Northview may be closed for up to 30 consecutive days while work is performed by the contractor.

The Nixa Public Schools bus barn and local emergency services have been notified so they can plan alternate routes accordingly during the closure.

Residents along Foxwood Drive will be allowed access to and from their residences during construction, but they should expect the possibility of delays when work is being performed.

Construction on this project will begin Friday with milling of the current road surface, despite temporary lane closures with flaggers, the road will remain open until Monday, November 13th.

June 2, 2023

Construction Beginning Soon

A construction contract has been awarded to Blevins Asphalt for the expansion of the roundabout. Expect multiple road closures. This is scheduled to be completed by August 15th.