Splash Pad

Project Summary

Nixa Parks and Recreation is Adding a Splash Pad!

Status

Project Quick Facts

Budget:

$650,000.00

Contractor:

Branco Enterprises Inc.

Anticipated Completion Date:

April 30, 2025

Status

We are thrilled to announce that Nixa Parks and Recreation is expanding our amenities with the construction of a brand-new Splash Pad, located next to the Aquatics Center on the west side. This long-requested feature will provide fun and refreshing opportunities for the community.

The project is funded through Impact Fees that have been saved for a new development of this scale. The splash pad construction has begun and will continue into the fall, with an expected opening in May 2025. Stay tuned for updates as the construction work progresses! We cannot wait for the community to enjoy this exciting new amenity next year!

September 24, 2024

Clearing & Excavating

Branco is working on site clearing and excavating for the splash pad.

September 19, 2024

Splash Pad Site Clearing

Branco has started working on clearing the site for the splash pad.

  Â